The high bay is now weather tight with the completion of the roofing, metal siding and precast concrete panels. Press pit is approximately 60% complete. Structural steel demolition is underway so all inside concrete work is on hold until demolition is complete. The demolition should be complete by Thursday or Friday of this week then concrete work will resume. The goal still remains to have the project ready to receive the Press on Tuesday September 15, 2009. We are working 7 days a week two shifts of 10 hours per shift.