Lockheed Martin - L-10 Hanger Door Rail Replacement
Finishing up Phase III of IV - new rails have been installed and we are
in the process of pouring back the grout bed. This work will be
complete early next week. Lockheed has elected to wait until December
to begin Phase IV due to positioning of the C-5 aircraft in the hangar.
After completion of Phase III we will drop back and replace the
pedestrian doors that are located within the hangar doors.