The following portfolio showcases some of Swofford Construction's most recent projects.
|
|
Stockbridge Middle School Additions and Renovations
Third phase will be turned over to the Owner to start moving in on Monday September 14, 2009... |
|
|
McEachern High School Stadium Improvements
Project in progress. More information coming soon... |
|
|
Lanier High School
We are working on the final site inspection items. This will take another week to complete and we will be 100% finished and off site... |
|
|
Dogwood Church
Project in progress. More information coming soon... |
|
|
Lockheed Martin - L-10 Hanger Door Rail Replacement
Finishing up Phase III of IV - new rails have been installed and we are in the process of pouring back the grout bed. This work will be complete early next week... |
|
|
Pratt & Whitney C4 Isothermal Forge Press Cell Facilities Modifications
The high bay is now weather tight with the completion of the roofing, metal siding and precast concrete panels. Press pit is approximately 60% complete... |